Rohbau
|
Monat
|
April
|
Mai
|
Juni
|
Juli
|
Kalenderwoche |
16 |
17 |
18 |
19 |
20 |
21 |
22 |
23 |
24 |
25 |
26 |
27 |
28 |
29 |
Fundament |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Bodenplatte |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Erdgeschossdecke |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Bautreppe |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Gerüst |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Giebel |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Dachstuhl |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Dacheindeckung |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fenster |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Außenputz |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Ausbau
|
Monat
|
Juni
|
Juli
|
August
|
Kalenderwoche |
22 |
23 |
24 |
25 |
26 |
27 |
28 |
29 |
30 |
31 |
32 |
33 |
34 |
35 |
Trockenbau roh |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Trockenbau fertig |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
HLS / Elektro |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Blower Door Test |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Innenputz |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Estrich |
|
|
|
|
|
Trockenzeit |
|
|
|
|
Heizung fertig |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Elektro fertig |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fließen |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Sanitär fertig |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Innentüren |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Treppe |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|